Riverhills June Construction Update
Posted
7 June 2022
Welcome to our latest Riverhills Construction Update.
We are delighted to announce it has been another productive month for the Riverhills team. Phase one works on the wetlands are progressing nicely and we hope to showcase this community feature soon. As mentioned last month, this will be followed by a significant landscape upgrade including new trees and a pedestrian trail – stay tuned for more information as this progresses!
Next time you visit, keep an eye out for our estate entry feature and updated signage on Epping and Craigieburn Roads to promote our wonderful community.
We are pleased to provide you with the below stage updates and look forward to touching base with you again soon.
Stage 3 – Phase 2 (Earthworks and Road Boxing) – Completed
This is where the big machinery first rolls in and involves preparation of the site to achieve ultimate design levels including site scraping and shaping of the existing ground.
Stage 3 – Phase 2 (Sewer & Drainage) – Commenced
Waste and stormwater systems are constructed and connected to each lot.
Stage 4 – Phase 1 (Plans & Permits)
This primary phase involves working with Council and other Authorities to secure planning approvals and acceptance of documentation including engineering designs to allow physical works to commence on site.
Did you know you can now track the progress of your lot on the Riverhills website? Visit Your Riverhills to access live updates of your stage at any time!