Secure land with just a 5% Deposit^ | Learn More

Riverhills May Construction Update

Welcome to our latest Riverhills Construction Update.

The project team has been busy at work with Phase One of the Riverhills major wetland progressing well and on track for an anticipated completion in the second quarter of this year. This will be followed by a significant landscape upgrade including new trees and a pedestrian trail – stay tuned for more information as this progresses!

We are pleased to provide you with the below stage updates and look forward to touching base with you again soon.

Stages 3 – Phase 2 (Earthworks and Road Boxing) – Completed

This is where the big machinery first rolls in and involves preparation of the site to achieve ultimate design levels including site scraping and shaping the existing ground.

Stages 3 – Phase 2 (Sewer & Drainage) – Commenced

Waste and storm water systems are constructed and connected to each lot.

Stages 4 – Phase 1 (Plans & Permits)

This primary phase involves working with Council and other Authorities to secure planning approvals and acceptance of documentation including engineering designs to allow physical works to commence on site.

Did you know you can now track the progress of your lot on the Riverhills website? Visit Your Riverhills to access live updates of your stage at any time!